Ordering a wire-DED or WAAM system does not create production capability. The machine must arrive in a verified configuration, connect safely to the site and then perform with representative material and geometry. This guide structures evidence from factory acceptance testing (FAT) through site acceptance testing (SAT) and the start of process qualification.

1. Requirement and system boundary

Define the part family, wire, shielding gas, deposition rate, work envelope, layer height, thermal and geometric requirements. Include robot or gantry, power source, feeder, gas, extraction, positioner, software, data logging and safety in the cell boundary. Every excluded element needs an interface and owner.

2. FAT at the supplier

Verify ordered configuration, axes, coordinate system, wire feed, power-source range, alarms, emergency stops, recipe control and data export. Run a repeated reference deposition with the contracted material. Exit criteria need measured geometry, mass, process signals and a controlled punch list—not merely a moving machine.

3. Pre-shipment documentation

Freeze hardware and software versions, calibration certificates, electrical and gas drawings, parts list, risk assessment, maintenance and backup procedures. Carry open deviations with owners and dates; a verbal promise is not acceptance evidence.

4. IQ and site safety

Verify foundation, electricity, cooling, gas quality and flow, extraction, fire protection, optical protection, access control and material handling. Record serial numbers, network configuration and interlock tests. Different utilities or layout can create new risks.

5. SAT re-establishes capability

Repeat the reference task at the site. Measure path accuracy, wire current, energy signal, gas state, deposited mass, wall geometry and thermal history. A pre-agreed equivalence band should determine whether post-shipment results match FAT.

6. Material and coupon plan

Trace wire lot, diameter, surface, chemistry and storage. Coupons should cover position, direction, starts/stops, intersections and heat accumulation. Density, macro/microstructure, tensile strength, hardness and, where relevant, fatigue or corrosion connect the process to requirements.

7. Downstream process and measurement

Deposition is intermediate. Heat treatment, stress relief, separation, machining, finishing and NDT can change the result. Verify measurement capability and datums; weak measurement can create false acceptance or unnecessary scrap.

8. Capability and ramp

One successful wall is not process capability. Use repeated builds, shifts and relevant envelope positions to estimate variation, first-pass acceptance, downtime and rework. Calculate capacity across the complete cycle from programming through final inspection.

9. Service and change control

Define response time, remote access, spares, preventive maintenance, software updates and recalibration. Before changing wire, gas, power source, head, software or path, specify which evidence must be repeated. A good acceptance package also provides a rollback point.

10. Minimum release gate

Production begins only when critical deviations are closed, configuration identified, operators trained, measurement capable, reference deposition repeatable and the part-specific qualification plan approved. SAT starts qualification; it does not replace it.

Contractual acceptance matrix

Assign each requirement a proof method: document review, inspection, functional test or measurement. Record sample count, instrument, uncertainty, acceptance limit, owner and record location. A contract that merely says the machine must work leaves geometry, properties and availability open to conflicting interpretations.

Fault injection and safe recovery

Under controlled conditions, test wire depletion, gas-pressure loss, power-source fault, communication loss, overheating and emergency stop. Verify safe state, retained logs and a restart that cannot continue with the wrong reference or recipe. Recovery should be executable by trained operators and auditable.

Example evidence package

A releasable reference build should contain the approved path file and checksum, machine and software IDs, wire and gas lots, calibration state, environmental and process signals, alarms, operator, post-processing and inspection results. This allows later deviations to be traced to material, machine, program, environment or measurement changes.

Sources and scope

This framework applies general equipment-acceptance and additive quality principles to wire DED. ISO/ASTM terminology, ISO 12100 machinery risk assessment and application-specific material and welding rules can be used together; contracts and regulatory requirements take precedence.